Industrial Electricity Load Sanction & CEI Approval

শিল্প বিদ্যুৎ লোড অনুমোদন

Factories need a high-tension (HT/11kV or higher) connection sanctioned by the power utility (DESCO, DPDC, BREB, BPDB, WZPDCL, NESCO) and the substation/electrical layout approved by the Office of the Chief Electrical Inspector.

Authority

Power utility (DESCO / DPDC / BREB / BPDB) + Office of the Chief Electrical Inspector

Processing time

Typically 1–3 months depending on load and line work.

Validity

Connection remains while bills and safety rules are met.

Legal basis

Electricity Act 2018 and rules (confirm)

Who needs it?

New or expanding factories with industrial load or their own substation.

Government fees

Government fees only — paid to the authority. Our professional fee is quoted separately, in writing. Each line shows how it was verified and when.

ItemAmountStatus
Application fee, security deposit and demand chargeAs per utility tariff and load — confirmConfirm with our office

Required documents

Standard

  • Application with load calculation
  • Land/rent documents and trade licence
  • Substation and electrical single-line drawing by licensed engineer/contractor
  • CEI approval of installation
  • Company papers and NID

Step-by-step process

  1. 1

    Calculate load and design substation.

  2. 2

    Apply to the utility.

  3. 3

    CEI approves the electrical installation.

  4. 4

    Pay deposit/demand note; line and meter installed.

  5. 5

    Energisation.

Frequently asked questions

Who approves my substation?

The Office of the Chief Electrical Inspector approves HT installations before the utility energises them.

Legal basis & official sources

Last reviewed 24 Oct 2026 by Legal Zone Business Licence Desk. Fees and rules change — we reconfirm every figure before you pay.

Related

Industry & Factory

Factory Licence & Layout Plan Approval (DIFE)

কারখানা লাইসেন্স (ডাইফ)

Factories, industrial and commercial establishments, shops, banks and insurers register and take a licence from DIFE. Layout plan approval, licence and renewal applications are filed online on the LIMA portal, where licences can also be verified.

⏱ Depends on inspection; plan for 2–6 weeks

Industry & Factory

Building Plan Approval & Occupancy Certificate

ভবন নকশা অনুমোদন ও অকুপেন্সি সনদ

Factories and commercial buildings need land-use clearance, building construction approval and, after completion, an occupancy certificate from the development authority — RAJUK (Dhaka), CDA (Chattogram), KDA (Khulna), RDA (Rajshahi) or the local municipality.

⏱ Land-use clearance and plan approval typically 1–3 months; occupancy certificate after completion inspection

Import & Export

Bond Licence (Customs Bonded Warehouse)

বন্ড লাইসেন্স

A customs bond licence lets 100% export-oriented manufacturers import raw materials duty-free under bond. It is issued by the Customs Bond Commissionerate after document scrutiny and physical inspection.

⏱ document scrutiny

Ready to get your Industrial Electricity Load Sanction & CEI Approval?

Send us your documents — we check them free and tell you exactly what's missing.