Factory Licence & Layout Plan Approval (DIFE)

কারখানা লাইসেন্স (ডাইফ)

Factories, industrial and commercial establishments, shops, banks and insurers register and take a licence from DIFE. Layout plan approval, licence and renewal applications are filed online on the LIMA portal, where licences can also be verified.

Authority

Department of Inspection for Factories and Establishments (DIFE)

Processing time

Depends on inspection; plan for 2–6 weeks (confirm current DIFE service charter).

Validity

One year; renew annually.

Legal basis

Bangladesh Labour Act 2006 (sections 3A, 326)

Who needs it?

Any factory, industrial or commercial establishment, shop, bank or insurance office covered by the Bangladesh Labour Act.

Government fees

Government fees only — paid to the authority. Our professional fee is quoted separately, in writing. Each line shows how it was verified and when.

ItemAmountStatus
Establishment licence / renewal by workers (non-factory productive establishments)0–1: Tk 100/50 · 2–3: 200/70 · 4–6: 400/100 · 7–10: 500/200 · 11–15: 1,000/300 · 16–20: 1,500/500 · 21–25: 2,000/700 · 26–30: 3,000/1,000 · 31–35: 3,500/1,500 · 36–40: 4,000/2,000 · 41+: 5,000/3,000Source: Bangladesh Labour Rules 2015 schedule (gazette 15 Sep 2015)Official document — reconfirmChecked 11 Oct 2026
Factory licence feeSet by workers and power — confirm on LIMA before paymentSource: lima.dife.gov.bdConfirm with our office

Required documents

Standard

  • Form-77 online application
  • Trade licence
  • Fire licence
  • NID of owner/MD/manager
  • Rent deed or land record
  • Electricity demand note
  • MoA or partnership deed
  • Approved factory layout plan (2 sets: flow chart, site plan, elevation, section, floor plan)
  • Approved building plan; structural design and load-bearing certificate for pucca buildings
  • List of workers
  • Treasury challan for the fee
  • Environmental clearance where applicable

Step-by-step process

  1. 1

    Get the factory layout plan approved on LIMA.

  2. 2

    Apply for the licence on LIMA (Form-77) with documents.

  3. 3

    Pay the fee by challan.

  4. 4

    DIFE inspection.

  5. 5

    Download the licence; verify it on the LIMA licence-verification page.

  6. 6

    Renew every year.

Frequently asked questions

Can I check whether a factory licence is genuine?

Yes — DIFE's LIMA portal has a public licence-verification page.

Is BIDA OSS linked with DIFE?

Yes, DIFE accepts applications through BIDA One Stop Service as well.

Legal basis & official sources

Last reviewed 22 Oct 2026 by Legal Zone Business Licence Desk. Fees and rules change — we reconfirm every figure before you pay.

Related

Industry & Factory

Fire Licence

ফায়ার লাইসেন্স

A licence from Fire Service and Civil Defence for warehouses, factories and premises storing or processing goods. It is a prerequisite for industrial trade licences, factory licences, IRC/ERC and bond licences.

⏱ Typically 7–30 working days including site inspection

Industry & Factory

Environmental Clearance Certificate (ECC)

পরিবেশ ছাড়পত্র

Industries and projects need site/location clearance and an Environmental Clearance Certificate from the Department of Environment (DoE). Your industry's class — Green, Yellow, Orange or Red — decides the route and fee.

⏱ roughly 15–30 working days

Sector Licences

Manpower Supplier / Labour Contractor Licence (DIFE)

জনবল সরবরাহকারী লাইসেন্স

Companies that supply workers to factories and establishments need a contractor licence from DIFE with a security deposit by size class.

⏱ Typically several weeks including inspection